优质的环氧地坪漆工程需要经验丰富的施工人员操作才能完成。那么环氧地坪漆怎么施工呢?相关环氧地坪工程:防静电地坪漆、环氧自流平地坪、地板漆、环氧地坪漆价格、环氧地坪漆施工、环氧地坪施工工艺环氧地坪漆怎么施工?
The high quality epoxy floor paint project needs experienced workers to complete the operation. So how to construct epoxy floor paint? Relevant Epoxy Floor Project: Antistatic Floor Paint, Epoxy Self-leveling Floor Paint, Floor Paint, Floor Paint Price, Floor Paint Construction, Epoxy Floor Construction Technology How to Construct Epoxy Floor Paint?
1、素地处理:①素地以水泥粉光或磨石为准,素地养生28天以上;②环氧砂浆找平地面,施工前保证素地干燥和清洁;2、底涂层:①施工前将双组份材料充分搅拌,需在4小时内施工完毕;②底涂层养生硬化时间8小时以上。
1. Plain ground treatment: 1. Plain ground is maintained for more than 28 days on the basis of cement powder or grindstone; 2. Epoxy mortar levels the ground to ensure that it is dry and clean before construction; 2. Primary coating: 1. Fully mixing the two-component materials before construction, which needs to be completed within 4 hours; 2. Curing and hardening time of primer coating is more than 8 hours.
3、中涂层:①施工前将主剂和固化剂按比例混合搅拌,再在混合完成的环氧树脂加入石英砂;②使用镘刀将材料均匀涂布,材料在30分钟内施工完成;③施工交接处做好交接处理,中涂层养生时间8小时以上;4、批刮腻子①将主剂和固化剂混合搅拌;②使用刮刀将材料均匀涂布,材料在30分钟内施工完成;③环氧腻子硬化时间8小时以上,最终达到平整无孔,无刮刀印为准。
3. Medium coating: 1) mix the main agent and curing agent proportionally before construction, and then add quartz sand to the epoxy resin mixed; 2) coat the material evenly with a trowel and finish the construction within 30 minutes; 3) do the handover treatment at the construction junction, and the curing time of the middle coating is more than 8 hours; 4) batch scraping putty (1) mix the main agent and curing agent; 2) use a scraper to mix the main agent and curing agent; Material uniformly coated, material construction completed in 30 minutes; 3. Epoxy putty hardening time of more than 8 hours, eventually to flat and non-porous, no scraper prints prevail.
5、面涂层①施工前需保持干净如有杂物粘附需清除;②使用前主剂先搅拌均匀;③依照正确比例将主剂及硬化剂混合,充分搅拌;④使用滚筒或镘刀将材料均匀涂布混合完成材料需30分钟以内施工完成。
5. Surface coatings should be kept clean before construction. If there is any debris adhesion, they should be removed. 2. Before use, the main agent should be stirred evenly. 3. The main agent and hardening agent should be mixed according to the correct proportion and fully stirred. 4. It takes 30 minutes to finish the construction of materials by uniform coating and mixing with drums or trowels.
⑤施工交接处需做好交接处理;⑥施工完成后,24小时后方可上人,72小时后方可重压,以25℃为准,低温时开放时间需适度延长。
Handover treatment should be done at the construction handover site; After completion of the construction, people can go to work 24 hours later, after 72 hours, heavy pressure can be applied, whichever is 25 C. Opening time at low temperature should be prolonged moderately. 本站网址:http://www.wuxispeed.com
|